PMP認(rèn)證考試練習(xí)題及參考答案(三十一)
1 The critical path in a network is the path that: 
A Has the greatest degree of risk. 
B Will elongate the project if the activities on this path take longer than anticipated. 
C Must be completed before all other paths. 
D All of the above. 來源:www.examda.com
E A and B only. 
ans:B 
2 The major difference between PERT and CPM networks is: 
A PERT requires three time estimates whereas CPM requires one time estimate. 
B PERT is used for construction projects whereas CPM is used for R & D. 
C PERT addresses only time whereas CPM also includes cost and resource availability. 
D PERT requires computer solutions whereas CPM is a manual technique. 
E PERT is measured in days whereas CPM uses weeks or months. 
ans:A 
3 A calendar that identifies when a project may be performed on an activity is called a: 
A Project calendar. 
B Resource calendar. 
C Milestone point. 
D Key point. 
E Work unit. 
ans:A 
4 Planning activities such that predetermined resource availability pools are not exceeded is called: 
A Resource leveling. 
B Manpower leveling. 
C Resource limited planning. 
D Manpower planning. 
E Manpower contingency planning. 
ans:C 
5 A comparison of completion status to baseline is referred to as _____. 
A Earned value measurement. 
B Percent complete. 
C ACWP. 
D BCWS www.Examda.CoM
E None of above. 
ans:A 
6 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: 
A Slack 
B Free float. 
C Restricted float. 
D Level float. 
E Lag 
ans:E 
7 Overlapping activities on a project, such as design and construction, is referred to as: 
A Fast tracking 
B Risk conversion. 
C Parallel management. 
D Process improvement. 
E Synchronous manufacturing 
ans:A 
8 A computer tape which contains historical project information is called ____ tape. 
A Database 
B Baseline. 
C Archive. 來源:www.examda.com
D Lessons learned. 
E Life cycle summary. 
ans:C 
9 Which method shown below is acceptable for reducing cost or shortening the schedule? 
A "Crashing" 
B Changing scope. 
C Performing activities in parallel rather than in series. 
D All of the above. 
E A and C only. 
ans:D 
10 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. 
A Increase, decrease. 
B Increase, increase 
C Increase, increase or decrease. 
D Decrease, decrease. 
E Decrease, increase. 
ans:B 
11 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling 
D Quantification. 
E None of above. 
ans:A 
12 Smoothing out resource requirements from period to period is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling. 
D Quantification 
E None of above. 
ans:C 
本站推薦
- 1PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目一馬當(dāng)先?答案當(dāng)然是肯定的!
 - 2項(xiàng)目進(jìn)度管理有難題?PMP系統(tǒng):一問就知,輕松解決
 - 3PMP項(xiàng)目管理,項(xiàng)目進(jìn)度管理的疑問終結(jié)者,您還在等什么?
 - 4項(xiàng)目進(jìn)度難掌控?PMP管理系統(tǒng):疑問解答,效率倍增!
 - 5PMP項(xiàng)目管理進(jìn)度系統(tǒng),能否讓您的項(xiàng)目效率翻倍?答案就在這里!
 - 6項(xiàng)目進(jìn)度滯后?PMP管理系統(tǒng):一問就知道怎么加速!
 - 7項(xiàng)目管理不再迷茫,PMP進(jìn)度系統(tǒng):您的疑問我來答
 - 8PMP在手,項(xiàng)目進(jìn)度管理難題還用問嗎?輕松搞定
 - 9還在為項(xiàng)目進(jìn)度頭疼?PMP管理系統(tǒng)幫您一問解千愁!
 