2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案33
QUEST Which of the following is equivalent to a lump sum contract: 
A fixed price contract 
B price fixing contract 
C purchase order 
D All of the above. 
E B and C only 
參考答案:A
QUEST Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party: 
A free on board 
B receipt for merchandise 
C packaging list 
D loading list 
E bill of lading 
參考答案:E
QUEST Which of the following is associated with a buyer's request for material to meet a particular need: 
A material warranty 
B material guarantees 
C implied warranty of salability 
D implied warranty of fitness for a particular purpose 
E A and C only 
參考答案:D
QUEST The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as: 
A post project evaluation 
B post contract evaluation 
C post mortem 
D procurement performance evaluation 
E contractor's performance evaluation 
參考答案:E

QUEST Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified: 
A beneficial completion 
B substantial completion 
C project completion 
D contract closeout 
E final completion 
參考答案:B
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案32
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
 - 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
 - 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
 - 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
 - 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
 - 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
 - 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
 - 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
 - 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)
 