2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案四十二
QUEST Using the situation stated in the Special window,  what is the cost performance index for Case #9? 
A 1.1 
B 1.91 
C 0.83 
D 1.2 
E None of the above 
參考答案:A
QUEST Sunk costs are: 
A future costs held in reserve. 
B costs invested in commodities. 
C expended costs over which we have no control. 
D expended costs over which we have no more control 
E tax credits 
參考答案:D
QUEST Managerial Reserves are: 
A allowances to account for price changes that can occur over the life of a project. 
B incentive fees paid to managers for good performance. 
C funds used to offset poor cost or schedule estimates. 
D accounts to allocate and maintain funds for contingency programs 
E All of the above. 
參考答案:D
QUEST Life Cycle Costing: 
A is the concept of including all costs within the total life of a project. 
B is an activity devoted to optimizing cost/performance 
C is an activity of appraising the cost and technical performance of a completed project. 
D is a process of predicting the life of a project. 
E None of the above. 
參考答案:A

QUEST Using the situation stated in the Special window,  what is the schedule variance for Case #8? 
A 1000 
B 2000 
C -1000 
D -2000 
E 0 
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案四十一
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
 - 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
 - 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
 - 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
 - 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
 - 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
 - 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
 - 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
 - 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)
 