2010年P(guān)MP美國項目管理考試習(xí)題及答案30
QUEST The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
A Payment authorization
B Bid cost considerations
C Release payment
D Back charge
E None of the above.
參考答案:D
QUEST Cost Reimbursable contracts are equivalent to:
A Cost plus contracts
B Fixed plus contracts
C Progress payment contracts
D Back charge contracts
E None of the above.
參考答案:A
QUEST Which is not part of the purchasing cycle?
A Defined need
B Transmit need
C Inspection
D Prepare and issue purchase order
E A and D
參考答案:C
QUEST Which is not an element of procurement management?
A Purchasing
B Expenditure
C Marketing
D Inspection
E B and D
參考答案:C

QUEST Which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process of arriving at an agreement prior to the award of a contract?
A Sealed bidding
B Competitive proposals
C Noncompetitive proposals
D Formal bid
E Verbal bid
參考答案:B