2010年P(guān)MP美國項目管理考試習(xí)題及答案三十五
QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. 
A Increase, decrease. 
B Increase, increase 
C Increase, increase or decrease. 
D Decrease, decrease. 
E Decrease, increase. 
參考答案:B
QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling 
D Quantification. 
E None of above. 
參考答案:A
QUEST Smoothing out resource requirements from period to period is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling. 
D Quantification 
E None of above. 
參考答案:C
QUEST Guidelines for estimating time durations include: 
A Assuming a normal  level of labor and equipment. 
B Assuming a normal work week. 
C Using consistent time units 
D Using past actual durations as guides. 
E All or part of each of the above. 
參考答案:E

QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed? 
A PERT 
B ADM 
C PDM 
D All of the above. 
E A and C only. 
參考答案:C